Fiber-Optic Construction Status January 7, 2022

Internet Sign

As of the week ending January 7 Charter Communications has completed the construction of 55% of its fiber-optic network in town. Crews have strung 198,617 feet (37.6 miles) of fiber-optic and metallic support cable on public roads. Charter still estimates the network being constructed in Sandisfield will require 362,517 feet (68.7 miles) of fiber-optic cable and the supporting metallic cable. At this time Charter anticipates starting the process of connecting properties to the network by the end of April this year. Activation of the network will be launched in town in 3 phases. Information associated with the network activation plan will be provided by Charter once the network construction phase has been completed.  

Stay tuned every month for all the latest information regarding the network construction status, getting connected to the network, service options, and the network activation plan.

Broad Band TRuck inSandisfield