Broadband Committee News & Announcements

Internet Sign

Fiber-Optic Construction Status March 1, 2022

As of March 1 Charter Communications has completed the construction of 83% of its fiber-optic network in town. Crews have... more ››

Internet Sign

Fiber-Optic Construction Status February 1, 2022

As of February 1 Charter Communications has completed the construction of 67% of its fiber-optic network in town. Crews... more ››

Internet Sign

Fiber-Optic Construction Status January 7, 2022

As of the week ending January 7 Charter Communications has completed the construction of 55% of its fiber-optic network in... more ››

Internet Sign

Fiber-Optic Construction Status Dec 6, 2021

As of the week beginning December 6 Charter Communications has completed the construction of 47.5% of its fiber-optic... more ››

Internet Sign

Fiber-Optic Construction Status Nov 1, 2021

As of the week beginning November 1 Charter Communications has completed the construction of 31.3% of its fiber-optic... more ››

Internet Sign

Fiber-Optic Construction Status Oct 12, 2021

As of the week ending October 8 Charter Communications has completed the construction of 27.1% of its fiber-optic network... more ››

Internet Sign

Fiber-Optic Construction Status Sept. 21, 2021

As of the week ending October 8 Charter Communications has completed the construction of 27.1% of its fiber-optic network in town. Crews... more ››

Internet Sign

Broadband Construction Begins! June 21, 2021

As of June 21, 2021, execution of the project make-ready process steps is near completion. Charter Communications plans to begin... more ››